Footprint Architects are delighted to have completed the new development at Linwood School. The development offers the a bespoke learning environment for up to 54 children with profound and multiple learning difficulties. The building was constructed using the latest offsite construction techniques and was delivered in just 6 months from commencing on site! #Bournemouth #Education...
Read More
It’s great to see the progress on site  at Linwood School, as the timber cladding is now being installed! #Architecture #Linwood #Modular #Timber
Read More
See how Linwood School development came together over two days in just 60 seconds! Video by Allan Searle – Linwood School   #Architecture #Modular #Bournemouth #Education
Read More
Amazing progress at Linwood School as the modular building is put together on site in just 2 days! #Architecture #Modular #Linwood #Bournemouth #Education @Modulek_LTD @bournemouthbc
Read More
animated architectural drawing of the red brick extension and red and white transparent extension at Downton primary school
Footprint Architects are excited to announce that our contemporary classroom development at Downton Primary School has begun on site! The two storey development provides additional KS2 classrooms, group space and ancillary accommodation for the primary school. The concept provides unique contemporary teaching spaces that allows the school to expand from a 1FE to a 1.5FE, yet ensuring that the overall...
Read More
Footprint Architects have submitted planning for phase 3 of works to Downton Primary School. The works includes two additional KS2 classrooms, communal group space, a new toilet block. It also includes an extension to the existing hall to make the school compliant with BB103 requirements. In addition the school seeks to expand its playing field onto...
Read More
Springwood ASD school has been completed and handed over.  The project included the refurbishment of an existing school building as well as the provision of a new modular building to form a sixty place specialist teaching unit. The school accommodates pupils from nursery to post sixteen and caters for children across the autistic spectrum.
Read More
LRC is on site! 1st Phase is complete and half the library is open for business. The PODs are constructed, balustrades clad and paint is now going on the walls . The photographs below reveal the current progress.
Read More
The interior of Downton Primary School is almost completed. The reception desk is finished and installed. The final touches include adding the wall and ceiling mounted TV’s.
Read More
The zinc soffit and fascia is being installed and the internal fit out is well under way. The external render coat will be applied in the next weeks and the green wall system will be fitted. More images after the break.
Read More
The glazing has been installed and the new reception is now weathertight.